Chapter 3. Planning and Protecting

Now that your organization is eager to adopt Scrum and a team has been selected with the right attitudes and abilities, it is time to snap into action and get the show on the road.

The following three shortcuts not only help you to set the team on their course but also give you some tips and tricks to keep the project on track.

Shortcut 7: Setting the Scrum Stage lays down a range of suggestions to ensure proper foundations have been established to support a successful Scrum team. Shortcut 8: Plan the Sprint, Sprint the Plan provides specific, practical advice to ensure an effective sprint planning session. Finally, Shortcut 9: Incriminating Impediments offers advice to help control the impact of impediments during sprint execution.

Shortcut 7: Setting the Scrum Stage

Scrum teams require chemistry, and just as in a science lab, successful “chemical reactions” are much easier to trigger when the broader organization provides the suitable ingredients and environment to work with. As Mike Cohn (2009) astutely recognizes, “The changes required to reap all of the rewards being agile can bring are far reaching. These changes demand a great deal from not only the developers but the rest of the organization as well.”

Let’s examine some of the key organizational and environmental preconditions that should ideally be considered as part of your Scrum adoption plan.

Ensure Team Stability

Tom DeMarco and Timothy Lister (1999) identify a key mantra that any organization seeking close-knit teams should adopt: “Preserve and protect successful teams.”

I am comfortable admitting that I have worked on Scrum projects that I would consider to be less than successful. I can easily pinpoint the core reason for these subpar results: my inability as a ScrumMaster to keep the team together for the duration of the project. This problem often occurs when key developers are dragged off one project to work on a more urgent project (see Figure 3.1). Couple this problem with continual corporate restructuring (that seems to be happening more and more in these times of global financial difficulty), and it can be challenging to preserve great teams.

Image

Figure 3.1. Beware of “more urgent” projects trying to drag team members away.

DeMarco and Lister (1999) also quantified the damage caused when rotating staff, concluding that “a reasonable assessment of startup cost (for a new team member) is therefore approximately three lost work-months per new hire.” This estimate doesn’t even take into account the less tangible costs such as lost momentum, damage to morale, and loss of valuable, tacit knowledge.

Adjust the Physical Environment

Without question, some of my most successful Scrum projects were those in which I was able to physically separate the Scrum teams from the rest of the organization.

DeMarco and Lister (1999) surmise why this may be the case:

It almost always makes sense to move a project . . . out of corporate space. Work conducted in ad hoc space has got more energy and a higher success rate. People suffer less from noise and interruption and frustration.

I’ve worked with Scrum teams that had to operate in large, open spaces near the sales team who were frantically on their phones all day, every day. I’ve also had teams that had been hamstrung by the corporate facilities department who wouldn’t allow them to move a small, measly round meeting table into their areas. I could go on and on, but the bottom line is that separation and environmental independence is the holy grail.

Irrespective of whether you are able to reach this lofty goal, you should do everything in your power to ensure that the Scrum team sits together. Scrum can certainly work for distributed teams where collocation isn’t possible, but it’s not optimal.

Apart from the obvious daily logistical benefits that sitting in close proximity offers, James Shore and Shane Warden (2007) offer an even more important rationale for the collocation of the team: “Sitting together is the most effective way I know to build empathy. Each group member gets to see that the others are working just as hard.” Shortcut 3 goes into more detail regarding other key inclusions to incorporate into the physical working environment to ensure a physical space conducive to Scrum.

Estimates Are Not Guarantees

How is this for an infuriating scenario? The project sponsor casually strolls over to a team member and asks how long feature XYZ is going to take. The team member takes off her headphones, breaking focus from what she was working on, glances up and throws out a rough estimate to appease the sponsor. Lo and behold, the estimate proves to be inaccurate. The sponsor then applies immense pressure on the entire team to deliver on the promised “commitment,” and dammit, if that means missing your kid’s end-of-year concert, then that’s the price of sticking to commitments!

News flash: An estimate is not a guarantee. If it were, there would be no need for the word. An estimate is simply a prediction based on known information and input at a given point in time. This definition needs to be clearly understood by the project stakeholders before the project kicks off!

Work toward Reciprocity

Mary and Tom Poppendieck, authors of Leading Lean Software Development, put forward the notion that there are two kinds of companies in this world: remuneration companies and reciprocation companies:

People who work in a remuneration company have this agreement with their company: “I will show up for work and you will pay me for my time. If you want more than that, pay me more.” On the other hand, people who work in a reciprocity company have this agreement: “I will treat you the way you treat me. I expect fair compensation, but if you want care and commitment on my part, then you agree that you will demonstrate care and commitment toward me, and you will help me develop my potential to its fullest extent.” (Poppendieck and Poppendieck 2009)

The best Scrum teams consist of committed and caring individuals, so it naturally follows that companies that embrace the reciprocity model are more likely than remuneration companies to have greater success with Scrum, especially in the long term.

Support Sustainable Development

Shortcut 1 mentioned that one of Scrum’s guiding principles is that team members should work at a sustainable pace.

In Agile Product Management with Scrum, Roman Pichler (2010) points out that

developing a product is like running a marathon. If you want to finish, you have to choose a steady pace. Many product owners make the mistake of pressuring the team to take on more work.

Any organization that maintains a culture of late-night martyrdom and continues to not only respect but also explicitly reward ludicrous overtime is at conflict with one of the principles of Scrum (or any other agile framework, for that matter). Overtime should be the exception, not the rule, and as recognized by Kent Beck in Extreme Programming Explained (1999), it should be recognized as “a symptom of a serious problem on the project,” not simply business as usual.

Run a Pilot Project

Although there are certainly some advantages to taking the Big Bang approach to rolling out Scrum across an organization, I don’t advocate it. Instead, I’m a big believer in initially running a pilot project. I recommend this approach even if the business is champing at the bit to roll Scrum out en masse. Why do I recommend investing this additional time if not to help obtain validation and buy-in? Mike Cohn (2009) explains the reason perfectly:

[A] pilot project is undertaken to provide guidance to subsequent projects; it pilots the way in doing something new. . . . As an industry we have enough evidence that Scrum works; what individual organizations need to learn is how to make Scrum work inside their organizations.

I always run pilot projects before rolling out across a broader group, and in fact, without the experimental freedom that a pilot project offers, I’m not sure if you would even be reading this book today!

It may be tempting to select a project to pilot that is low value and therefore low risk. This is a false economy. Shore and Warden (2007) reinforce this point:

Avoid taking a project with low value as a “learning opportunity.” You’ll have trouble involving customers and achieving an organizational success. Your organization could view the project as a failure even if it’s a technical success.

Regarding team stability and the less-than-successful projects I experienced: the reason I couldn’t keep those teams together was that the pilot projects we were working on were not of high enough priority and value. When push came to shove and shared resources were being stretched between the pilot project and the “more important” projects, no guesses as to which lost out.

How long should a pilot project last? Well, if you’ve been reading this section carefully, you will conclude that your pilot project should be no different from any other important project. As Roman Pichler (2010) states, “There is no rule in Scrum that mandates how long a project can last. But, it is common for agile projects to take no longer than three to six months.”

Have Realistic Expectations

Change takes time, and very often with change, we need to take one step back to take two forward. Adopting Scrum requires a significant shift in organizational mindset that includes breaking entrenched habits, and this feat doesn’t happen overnight.

There is going to be lead time before the developers feel comfortable working in cross-functional teams and before the old command-and-control attitudes disappear. Based on this premise, the organization should not be naïve and expect amazing gains immediately. Patience and nurturing is the name of the game, and a supportive organization will no doubt see its investment reaping dividends in the near future.

Shortcut 8: Plan the Sprint, Sprint the Plan

As one of the “elements of a chemistry-building strategy for healthy organizations,” DeMarco and Lister (1999) recommend providing “lots of satisfying closure.” I totally agree with their advice and suggest another complementary element: the provision of lots of clean, fresh starts. Luckily for us, the sprint time-box offers both closure and fresh starts, and in this shortcut we explore the Scrum activity that offers us the regular fresh start: sprint planning.

By collectively resetting the goals for the upcoming sprint every few weeks, the team can start afresh rather than remain stuck on a seemingly endless treadmill of ongoing work. Further, without this regular and expected planning session, significant disruption is caused when team members are rounded up on an ad hoc basis to plan and design.

Product Backlog Refinement

Before the team is gathered in the planning room, I recommend a few preliminary steps to ensure that the product backlog is refined appropriately. First, ensure that the product owner (with relevant assistance) not only has determined the next priority requirements for the upcoming sprint but also has fleshed them out in just enough detail to allow the developers to get started. Doing so might mean including more detailed acceptance criteria as well as any wireframes or mock-ups if applicable (see Shortcut 11). Additionally, it helps if the product owner has taken some time to collaborate in advance with any specialist testers to develop a set of initial test cases (based on the acceptance criteria) to fully describe the inner workings of the required functionality.

Goals Are Good

I would say that most of us enjoy working toward goals, so it is helpful to determine a centralized sprint goal that is omnipresent throughout the sprint. This focal goal typically maps to the main theme of the sprint. For example, the sprint goal might be Enhance the Messaging Engine; this doesn’t mean that other bits and pieces can’t also be worked on during the sprint, but it does indicate that the majority of the work will target the messaging engine. A sprint goal also helps with decision making by ensuring that everyone remains focused rather than deviating and heading off on tangents.

How Long Should a Sprint Be?

Back in the day, it was recommended that the sprint duration should be 30 days—no more, no less. These days, things have become somewhat more flexible, and it is now pretty much universally accepted that the sprint length can vary from team to team. If you speak to any Scrum team, you will find that the vast majority of sprints run from 1 to 4 weeks. I have tried them all out, and in my opinion, 1 week is too short, 4 weeks is too long, leaving me sitting on the fence between 2 and 3 weeks. For a new project, I make the decision based on two factors:

image Team preference: Some people prefer the longer duration to help gain more momentum, whereas others prefer the simpler planning that a shorter sprint offers.

image Volatility of requirements: If the product owner is likely to change requirements more often than not due to the product domain or market conditions, then I definitely recommend the shorter duration (see Figure 3.2).

Image

Figure 3.2. Factors to take into account when considering sprint length.

Now, an important point: When the preferred sprint length is confirmed (it may take some experimenting in the early days), it should be locked in and rarely changed. There are specific reasons to avoid sporadically adjusting the sprint length, including the following:

image For team focus, a regular rhythm helps the team better understand how to pace itself.

image The velocity metric (see Shortcut 13) relies on a consistent sprint duration; otherwise, it becomes less meaningful and more difficult to calculate.

image If you change the duration of sprints, your sprint review, retrospective, and planning sessions will not fall on the same day of the week. Such irregularities can prove to be a logistical headache, especially if you have to share meeting rooms with others in the organization.

Capacity Planning

Before diving into the sprint planning process, the team needs to first determine its sprint capacity. First, remember that not everyone will have full capacity for every sprint. Some team members may need to work across multiple projects—certainly not an ideal situation, but it can happen (see Shortcut 6). If this is the case, make sure that these developers aren’t overallocated. Also, don’t forget to take into account any public holidays, training, or scheduled leave.

Second, don’t fall into the trap of believing that those who are dedicated full time to the sprint will be able to spend their entire working day on sprint-related tasks.

For example, in a team that I recently worked with (using 2-week sprints), a full-time developer was typically allocated a capacity of 9 days × 6 hours per day = 54 hours per sprint to work on tasks.

First, we used 9 days because the equivalent of 1 full day was dedicated to the sprint planning, review, and retrospective sessions. Six hours a day was allocated because in a typical 8-hour day we found that an individual would usually get only about 6 hours of solid sprint-focused work. The rest of the time was often taken up by various other activities unrelated to the current sprint, such as refining the product backlog (in anticipation for the upcoming sprint) and more general tasks required to be a good citizen of the organization (such as responding to email and assisting others not in the Scrum team). Please note that the proposed capacity per day will vary depending on the team and environment. As such, 6 hours a day should not be considered a universal standard, and I recommend using historical sprint interference statistics (see Shortcut 19) to help you determine your team’s estimated sprint capacity.

Let’s now take a look at the flow of the actual sprint planning session, which I like to split into two distinct parts:

Part 1: The What

This segment is all about the product owner presenting the next-highest-priority product backlog items (PBIs) to the development team as well as fielding any specific questions. This task is conducted for each of the PBIs that are being targeted for completion in the upcoming sprint. I recommend using the team’s velocity (see Shortcut 13) as a rough guide to determine how many PBIs the product owner should be prepared to run through during this session.

Part 2: The How

Moving on, it is then time for the development team to break the PBIs into more granular technical tasks and to estimate each task to the nearest hour. Although estimating in hours may still be inaccurate at times, it helps the team make more informed design trade-off decisions and assists in establishing more confidence in what will likely be delivered by the end of the sprint. As Cohn (2007) explains further:

The goal is not the hours but the hours are often a good tool to use to ensure we have discussed things (mostly the technical and product design of those things) at a level sufficient to enter the sprint with a good feeling that we’ll be able to finish all the work of the sprint.

I don’t expect product owners to hang around for this second part (unless they particularly want to). That being said, I stipulate that although product owners don’t necessarily need to be in the room, they certainly need to be on call in case any further clarification is required. Nothing stalls a sprint planning session more than an unavailable product owner!

Even though I like to use velocity-based planning as a guide for Part 1, I like to also use what is commonly known as commitment-based planning to determine the number of specific tasks to include in the sprint backlog. Here are the steps that the development team typically runs through during commitment-based planning:

1. Start with the highest-priority PBI.

2. Deconstruct the PBI into tasks with estimates in hours.

3. Identify any specific task dependencies.

4. Continue this cycle until the team’s collective capacity is full.

5. If the output from the velocity-based approach (from Part 1) doesn’t match the output from the commitment-based approach, simply call back the product owner (if she has left the room) to add additional PBIs (if there is still capacity) or explain to her why there will be fewer PBIs targeted than initially expected (if the capacity is filled earlier than initially expected).

Task Definition

I typically set a few parameters for the generation of tasks:

image Each task needs to be a small, testable slice of the overall PBI (see Shortcut 10) and needs to factor in all activities required to meet the task’s definition of “done” (see Shortcut 11).

image Each task should take no longer than about 8 hours (the shorter, the better, though).

image Although more than one developer can work on a single PBI, there should be only one developer (or developer pair) working on a task (see Figure 3.3).

Image

Figure 3.3. Although a single PBI can be worked on by multiple developers, each task should be worked on by only one developer.

image Don’t forget to include tasks for the sprint review preparation (see Shortcut 22), such as preparing demo data if required.

You now have the sprint backlog compiled, including the tasks and corresponding estimates for them. The original estimates for the tasks can be aggregated to form the sprint’s initial remaining time, and this time can then be recalculated each day and tracked on the sprint burndown chart (see Shortcut 19). Before going home each day, everyone on the development team should adjust the remaining time for any tasks they had been working on that day to ensure that up-to-date data is being fed into the sprint burndown chart.

The Right Number of Requirements

In a perfect world, after sprint planning is all said and done, you will have a nice neat whole number of PBIs that the team anticipates it will be able to complete in the forthcoming sprint. What you will find occasionally is that there will be a small amount of expected capacity left over that isn’t quite enough to fit a whole new PBI into. That’s okay—simply acknowledge as a team that the intention is to commence the next-highest-priority requirement without setting the expectation that it will be completed by the end of the sprint. I prefer this approach to trying to identify a small enough PBI (lower down on the product backlog) that could fit in nicely because I feel that it is more important to focus on working on the highest business value items.

The 7 Ps

As the British army adage goes, “Proper planning and preparation prevents piss-poor performance,” so a thorough and well-conducted sprint planning session is important to help generate a forecast that is as accurate as possible.

The sprint won’t always go according to plan, and no doubt adjustments will need to be made at times. However, if this session is well run, everyone will have a much better idea of what the collective objectives are, and this information will make the coordination and alignment of expectations a great deal easier.

Shortcut 9: Incriminating Impediments

You’ve trained your new Scrum troops, and they’re ready for their first mission. The team is pumped, and the project is up and running. Things are going well; the daily scrums are happening, the continuous integration server is humming along, tasks are moving across the board, so life is pretty sweet. Then, from out of nowhere, the bullets start flying, the mines start exploding, and your troops are no longer moving forward. This is it, ScrumMaster—time to step up!

Okay, so perhaps in reality, it isn’t a spray of enemy fire impeding your team. Instead, it might be a constantly breaking build, an interfering project sponsor, or perhaps the loss of a key team member. The bottom line is that anything impeding your team’s progress becomes the number-one priority for the ScrumMaster to tackle.

Defining Impediments

Let’s start by defining what an impediment is. Here is the definition I choose to use:

An event that impedes any of the developers from working to their anticipated sprint capacity.

If you recall from Shortcut 8, it isn’t wise to allocate a full-time developer a sprint capacity of 8 hours a day (for a typical 8-hour working day). Why not? you ask. Well, you have to be realistic: there is no way that people are going to spend every second of their operational time working on their sprint tasks. We must take into account the various meetings that will pop up, other extended collaboration time, unplanned company events, and important head-clearing breaks, just to name a few. Now don’t get me wrong: on some days, some team members will be able to maintain strong focus on their sprint tasks and will max out or even exceed the 8 hours. However, on other days, constant interruptions may make it difficult to maintain even a couple of hours of sprint-focused work.

Many Shapes and Sizes

Impediments come in all shapes and sizes. Following is a small sample of indicative impediments (both operational and systemic) to keep a careful eye on:

image Meetings of large magnitude: Scrum projects really should have no need for these extraneous, long-winded bad boys, so when they pop up, they are typically triggered by other areas of the business or by unforeseen issues.

image Illness: Illness can strike unannounced at any time. Not much you can do about it, but I highly recommend you avoid a culture of “toughing it out” when sick. That expectation is just stupid. Work quality suffers, germs spread very quickly in an open Scrum environment, and it just annoys everyone.

image Broken builds: Without a healthy build (see Shortcut 18), development cannot continue. If a build is broken, it must be the top priority of every team member to fix it.

image Issues with the tools of the trade: Whether it is a hardware malfunction, software problem, or network connectivity issues, any problems with the working environment can seriously hamper progress and lead to immense frustration.

image Unreliable supplier: This is possibly one of the most frustrating impediments due to the lack of control that the ScrumMaster and team might have in dealing with an overburdened supplier. Poorly supported components or add-ons can lead to black holes that can seriously suck time from your sprints.

image Unrefined product backlog: A sprint should never start without the product owner knowing exactly what requirements should make their way into the sprint backlog. Further, these requirements should include enough detail for the development team get their teeth into. If these requirements are not ready for the sprint planning session then the sprint will not start smoothly at all (see Shortcut 11).

image Absent or unempowered product owner holding up key decisions: Product owners should be available throughout the sprint to field specific questions about the sprint backlog. If they are regularly absent or constantly having to seek approval from elsewhere, the development team might find itself paralyzed with uncertainty.

image Incentive schemes focused on the individual: Many organizations maintain performance reviews (and associated incentive schemes) that are based entirely on individual performance. Hopefully by now you’ve absorbed the fact that there is no “I” in “Scrum team,” so unless reviews also incorporate a significant focus on team collaboration, the organization will be sending a contradictory message to the team members.

Impediment ConTROL

I like to run through the following five-step approach when dealing with impediments: confirm, triage, remove, outline, learn (ConTROL).

image Confirm: Obviously it is necessary to confirm what the impediment is. Typically, impediments are raised in the daily scrum, but urgent impediments should be raised in real time rather than waiting for the daily scrum. The sprint retrospective can uncover further impediments that may have slipped through the cracks during the actual sprint. All impediments should be tracked and monitored until they are resolved.

image Triage: If you are bombarded with simultaneous impediments, then unless you are Superman (being obsessed with super heroes doesn’t automatically give you their special powers), you will be able to tackle only one or two at a time. An impact and urgency assessment may be needed to help you determine where to start.

image Remove: Ideally, the Scrum team can remove any impediment that gets thrown its way, but it isn’t always the reality. To avoid delays, it is important to know when to seek further help from other groups to get things back on track (see Shortcut 26).

image Outline: Both the Scrum team and stakeholders should be made aware of any impediments as they come up. You especially want to avoid surprises for product owners (and project sponsors) when it comes to any scuttled plans so that they have as much time as possible to iron out any cascade effects.

image Learn: The sprint retrospective (see Shortcut 23) is the main session during which impediments are analyzed. It is important to learn from these issues to avoid their recurrence and/or capture how they were dealt with so that if they strike again, the impact is less pronounced.

Blocks versus Impediments

Many teams use the terms block and impediment interchangeably, but I like to differentiate between the two (see Figure 3.4). I do so to clearly identify an obstruction that has stopped progress on a particular task but hasn’t necessarily slowed down overall progress (a block) versus an obstruction that is slowing down the team’s sprint progress (an impediment).

Image

Figure 3.4. A block affects only a single task, whereas an impediment acts like a parachute, slowing down overall progress.

A typical block occurs when a task has a dependency that has been held up for some reason. A short, temporary block is a reasonably common occurrence and nothing to get too concerned about, because in most cases, other work can be taken on while the dependency is being taken care of. The important thing to note is that you want clear visibility of all blocked tasks, irrespective of how temporary the block may be. The way I like to track blocked tasks is to simply spin the corresponding sticky-note 45 degrees so that it looks like a diamond and stands out on the task board. This is a clear signal and allows you to immediately jump into detective mode to ensure that the block is removed as quickly as possible.

Understand the Terrain

If you’re like me, you will be stunned when you think back to all of the impediments that occurred throughout a project. It is often only when you reflect on the compiled list of tracked impediments that you can really appreciate the difficult terrain your Scrum troops have had to negotiate.

This impediment list can also prove invaluable if ever you must defend the team should it fall under an uncomfortable spotlight due to incremental delays that have started to impact release dates. I certainly found that if you carefully ConTROL impediments when they decide to rear their ugly heads, these uncomfortable situations will be few and far between.

Wrap Up

The three shortcuts discussed in this chapter focused on a selection of tactics, tools, and tips to help you to set your team on course and keep them on track. Let’s recap what was covered:

Shortcut 7: Setting the Scrum Stage

image The importance of collocating team members whenever possible

image A selection of cultural adjustments that are required to ensure that Scrum can thrive

image How and why pilot projects can assist in longer-term Scrum adoption

Shortcut 8: Plan the Sprint, Sprint the Plan

image Factors to consider when selecting your sprint length and goal

image How to determine a realistic sprint capacity

image Options for structuring your sprint planning session

Shortcut 9: Incriminating Impediments

image Definitions of impediments and blocks

image Types of impediments to watch out for

image How to ConTROL your list of impediments